Prestigious Rattle Hydropower Project to be developed by JKSPDC

JK News Today

JAMMU, JANUARY 22: The Deputy Chief Minister Nirmal Singh today said a comprehensive Relief and Rehabilitation (RR) policy has been formulated for the affectees of three Power projects i.e. Pakal Dul, Kiru and Kawar in Kishtwar district wherein Rs 33 lakh would be provided for undertaking the construction for individual house, the extent of stamp duty would be limited to Rs 25 000 besides providing an amount of Rs 40,000 for construction of work shed and 25000 for cattle shed and providing a scholarship of Rs 1000 per month for undertaking studies of the children of  the affected families.

The Minister was replying to the discussion held on a starred question raised by Sajad Ahmad Kichloo in the Upper House today.

The Deputy Chief Minister said there are 4 power projects with 1680 MW cumulative capacity operational on River Chenab, while as 7 more projects having total capacity of 5388 MW have been proposed to be constructed on the river flowing through Chenab Valley comprising Kishtwar, Doda and Ramban districts.

Giving details of the commissioned power projects on River Chenab, the Minister said that Dulhasti Power Project with a capacity of 390 MW, Bhagliar Hydro Electric Project (BHEP) Stage-I and II with capacity of 450 MW each and Salal Hydro Electric Project (HEP) with capacity of 390 MW are operational and are generating power which is being supplied as per set norms.

Singh further informed the House that  7 more  Power projects having total capacity of 5388 MW include 1000 MW Pakal Dul HEP, 624 MW Kiru HEP, 540 MW Kawar HEP, 1856 MW Sawalakote HEP, 390 MW Kirthai-I, 930 MW Kirthai-II and 48 MW Lower Kalnai are proposed to be constructed on River Chenab. The Minister said that out of these projects 3 projects Pakaldul, Kiru and Kwar HEPs are in advanced stage of tendering while as final clearance is awaited at CEA for Sawlakote HEP.

Minister said that DPR for Kirthai-I project is under appraisal at CEA while as Kirthsai-II has been appraised by the CEA for which a consultant has been engaged for preparation of bid document for execution of project in EPC mode.

The Minister said that execution of Lower Kalnai Project at an estimated cost of Rs 576.87 crore has been taken by M/S Coastal Projects Limited, but only 10% progress has been achieved and due to poor performance of contractor the work is bound to get delayed. He said an amount of Rs 108.10 crore has been expended so far.

With regard to the 800 MW Burser HEP, the Minister said that the project is one among the 7 projects handed over to NHPC for development under central sector under an MoU in July, 2000 between the State government and the government of India. He said the project in under investigation and DPR preparation/appraisal. However, the project is yet to be cleared by government of India for construction, the Minister said.

The Minister said that in respect of  330 MW Wudwan-Bursar, 235 MW Barinium HEP, 230  MW Shous and 370 Shamnot projects PFR  has been prepared by JKSPDC through M/s WAPCOS which shall be followed by preparation of DPR and appraisal from the competent authority.

In respect of the 850 MW Rattle Hydroelectric Project (HEP), the Minister said that the project was awarded on BOOT basis to M/s GVK through tariff based competitive bidding. However, he said, the developer abandoned the project in the year 2014.  Minister said that the State government has terminated the PPA with the developer.

Singh further said that the project shall now be developed by Jammu and Kashmir State Power Development Corporation (JKSPDC). He said that the claims from the developer and the counter claims by the state government are under arbitration. He said that, to proceed further, JKSPDC on the directions of the State government has engaged the IIT-Roorkee for valuation of the assets created by the developer.

Deputy Chief Minister informed the House that JKSPDC does not engage the services on temporary basis and no staff is engaged specifically against the projects. He said that total 210 persons are at presently engaged in Chenab Valley Power Projects (P) Ltd including those on transfer or deputation basis from NHPC, State government and directly recruited by CVPP. He said among those116 are technical and 94 are non-technical.

The Minister informed the House that  416 employees of Dull Hasti Power Station, Kishtwar including technical and non-technical are on the rolls of NHPC while as 610 employees including technical and non-technical  of Salal Power Station, Reasi, are on the rolls of Corporation. He said the JKSPDC have centralized mode of recruitment based on the project requirement and in line with the procedures adopted in State government. Minister said that in CVPPL the recruitment for engagement of staff is being made through open advertisement.

Singh said that direct recruitment against the clear out vacancies for Executives and Supervisors is being done centrally by NHPC Corporate office after advertisement in Employment News, National Dailies or local newspapers as per the instructions issued by the central government where necessary written competitive examination, test for oral examination by means of interview of candidates by selection committee is held for recruitment.

The Minister said that no non local (non state subject) is placed on rolls of JKSPDC. However, he said, contractors engaged for execution of project recruit partly non-locals depending upon the requirement and insufficiency within state quota.

Earlier, several legislators including Sajad Ahmad Kichloo,       Fridous Ahmad Tak, Ghulam Nabi Monga, Ashok Khajuria, Naresh Kumar Gupta, Sham Lal Bhagat, Sofi Yousuf, Girdhari Lal Raina,          Surrinder Kumar Choudhary and Yasir Reshi participated in teh discussion and suggested various measures to streamline the power geberation and distribution system in the State.